PG&E 100A to 200A Panel Upgrade: Process and Cost Factors
In PG&E territory a panel upgrade is a customer-side electrical job coordinated with the utility. Knowing who does what helps you avoid surprises.
⚠️ Safety first: Work inside a panel or on a 240V circuit should be done by a licensed electrician, with a permit where your area requires one. This page explains the planning, not how to do the wiring.
Who does what
PG&E's panel upgrade guide says the customer, contractor or licensed electrician assesses the home's energy needs and submits a load evaluation request through PG&E's Your Projects Portal. PG&E assesses whether nearby infrastructure can handle the load, which the guide says can take up to 30 days. If infrastructure upgrades are needed, PG&E provides plans, cost estimates and a contract. You are responsible for permits and costs of the wiring work at your home, and the city inspector approves the new panel. PG&E disconnects and reconnects power; the guide says reconnection is typically within one day after the panel is replaced and inspected.
Costs
PG&E's guide says an initial advance of up to $5,000 for a single-family home may be required for the assessment, refunded or credited toward any balance owed. It gives no dollar amounts for design deposits or infrastructure work. Costs vary widely by home, location and scope, and utility rules change, so this page does not quote a price. Get written quotes from licensed electricians, ask your utility for its current requirements, and see our national panel upgrade cost guide for typical ranges.
Before you hire
- Ask whether the job needs a utility load evaluation or only a customer-side panel swap.
- Ask who pulls the permit and who schedules the disconnect.
- Confirm whether a meter socket or service conductors must be replaced.
- Ask whether load management or measured demand (see NEC 220.87) could avoid the upgrade.
Sources
Frequently Asked Questions
Q: Does PG&E do the panel upgrade?
A: No. A licensed electrician does the wiring work at your home. PG&E assesses its infrastructure and handles disconnects and reconnects.
Q: How long does PG&E take to assess a load request?
A: PG&E's guide says the assessment can take up to 30 days. Overall timelines vary.
Q: How much does it cost?
A: PG&E's guide gives no overall price. It mentions an advance of up to $5,000 for assessment, refunded or credited. Get local quotes.