Con Edison Service Upgrade: Process and Delays
Con Edison work requests are submitted by a licensed contractor through its Project Center, and the utility needs proof of municipal inspection before it connects service.
⚠️ Safety first: Work inside a panel or on a 240V circuit should be done by a licensed electrician, with a permit where your area requires one. This page explains the planning, not how to do the wiring.
The process
Con Edison's Building and Remodeling FAQ says electric and gas work must be completed by licensed plumbers or electricians, and that your licensed contractor submits the work request through Project Center. Con Edison reviews the request and sends a customer service installation agreement (the service layout). The contractor prepares the site and submits checklists; Con Edison verifies the site, then construction or meter work begins. After city or municipal certifications and applications, Con Edison performs a final inspection and orders connections, meter installation and turn-on.
Timing and fees
The FAQ says that if excavation is required, allow up to 90 days from the site inspection, and that a new meter averages about 10 days after all deposits, applications and the final inspection are complete. It says there is no fee for inspection services but re-inspection may be charged, and that tariff fees can apply to items such as temporary service or converting overhead to underground. No dollar amounts are given. Costs vary widely by home, location and scope, and utility rules change, so this page does not quote a price. Get written quotes from licensed electricians, ask your utility for its current requirements, and see our national panel upgrade cost guide for typical ranges.
Voltage in apartments and older buildings
Many older multi-family buildings and brownstones have services that differ from a typical suburban single-family home, so capacity and meter arrangements depend on the building. Ask Con Edison and a licensed NYC electrician what applies to your building before assuming a number.
Sources
Frequently Asked Questions
Q: Who applies for a Con Edison service upgrade?
A: Con Edison's FAQ says your licensed contractor submits the work request through Project Center.
Q: How long does it take?
A: The FAQ says up to 90 days from site inspection when excavation is needed, and about 10 days for a new meter after the final inspection. Delays can occur.
Q: How much does it cost?
A: Con Edison's FAQ gives no dollar amounts. Get quotes from licensed NYC electricians.