Utility Guide

ComEd 200A Upgrade: Conduit, Riser and Meter Rules

📅 Updated October 2026⚡ HomePanelCheck Editorial

ComEd's service and meter requirements put the service entrance conduit, wires and meter connection device on the customer, and require inspection before energizing.

⚠️ Safety first: Work inside a panel or on a 240V circuit should be done by a licensed electrician, with a permit where your area requires one. This page explains the planning, not how to do the wiring.

What ComEd says the customer owns

ComEd's Service and Meter Requirements say the customer owns the service head, service run wires (leaving at least 18 inches past the head), the riser or conduit, flashing where the run passes through a roof, and the meter connection device. ComEd owns the service drop, dead-end and the connectors joining the customer wires to the drop. The customer must tell ComEd the wire size.

Conduit, mast and meter details

The document lists rigid steel conduit sized 2-1/2 inch for 100A or less and 3 inch for larger service equipment, new service heads no more than 25 feet above ground, and attachment strong enough for 1,000 pounds of tension. Only meter connection devices with the CECHA marking are approved in ComEd territory. Check the current version of the document and your village or city rules, which may be stricter.

Inspection

The customer obtains permits and required inspections. The document says municipalities usually prohibit ComEd from connecting service to an installation that has not passed inspection, and that ComEd's own checks cover ComEd rules, not the National Electrical Code. For other details, ComEd lists its New Business line at (866) 639-3532.

Cost note

Costs vary widely by home, location and scope, and utility rules change, so this page does not quote a price. Get written quotes from licensed electricians, ask your utility for its current requirements, and see our national panel upgrade cost guide for typical ranges. Conduit and riser requirements are one reason Chicago-area service upgrades can cost more than a simple panel swap.

Sources

Frequently Asked Questions

Q: Who owns the service conduit in ComEd territory?
A: ComEd's requirements say the customer owns the riser or conduit, service head, service wires and meter connection device.

Q: What size conduit does ComEd require?
A: The document lists rigid steel conduit at 2-1/2 inch for 100A or less and 3 inch for larger service equipment. Check the current version.

Q: Does ComEd inspect to the NEC?
A: The document says ComEd's inspections check ComEd rules only and do not show NEC compliance.

⚡
Rahul T. — Founder & Editor, HomePanelCheck.com
Rahul researches home electrification, NEC load calculation methodology, and EV charging infrastructure to help homeowners understand their electrical panel options in plain English. This page is based on manufacturer documentation and NEC sources linked in the text. It is not a substitute for a licensed electrician's assessment of your specific home. Questions or corrections? contact@homepanelcheck.com
🍪 We use cookies for analytics and advertising to keep this tool free. Privacy Policy